Project Milestones can be moved back or forwards by a number of days. This is a useful tool if you have split your Project into multiple phases using Milestones, but the whole Project has been delayed, perhaps due to another Project running over.
To change dates of your Milestones:
- In the Project Screen, open the Milestones tab
- Select the Milestones you wish to move by ticking the checkboxes or using the All / None options
- Click Change Date
- Enter the number of days you wish to move the Milestones by
(Entering 3 will move Milestones three days later, -3 will move Milestones three days earlier)